Posts

Showing posts from August, 2019
Third month progress Hello visitors!!  I am here presenting you with my final month GSoC project report. I will be providing the links to my work at the end of the section. Final month of the work period was much more hectic and tiring than the first couple of months. I had been busy more than I had anticipated. Nonetheless, I had to write code which I enjoyed writing : ) . In the first half of this work period, I was focused on completing the left-over QDBus communication from the phase 2, which I did successfully. But as when I thought my task was all over, I was faced with some regression in the code, which I utilised my rest half a month to fix it. I will talk about it later in the post. Coming to the progress made during this period, I have done the following: Complete left-over QDBus communication from Phase 2 : During the first 2 months of the work period, I have completed the rest of the QDBus communication from Helper to Application. This was pretty easy to do, jus